|

MPC Protection Against Adverse Ordinance Changes Not Applicable
to Sewage Facilities Plans.
Pequea Township v. Herr et. al., 716 A 2d 678 (1998)
Cross Reference: MPC Section 508(4)(I)
The Commonwealth Court, in reviewing an order of the Environmental
Hearing Board, held that the protections afforded a developer
against changes to zoning and subdivision/land development ordinances
during the five (5) years following preliminary plan approval
do not protect against adverse changes to a municipalities sewage
facilities plan.
In this case a developer had obtained preliminary approval for
an industrial development, to be served by public sewer. Some
twenty (20) months later, the township adopted a revised sewage
facilities plan which changed the proposed method for treating
sewage for the parcel (as part of a larger treatment area) from
public to on-lot disposal systems. The new plan was filed with
DEP for review and approval under Act 537. Shortly thereafter,
and before approval of the new sewage facilities plan by DEP,
the township refused to adopt the sewage facilities planning module
submitted by the developer on the grounds that it was inconsistent
with their new sewage facilities plan.
Fourteen months later (still within the five (5) year protection
period under MPC 508(4)(I) the developer obtained final approval
from the county planning commission for his project, conditioned
upon approval of his sewage facilities planning module. The township
did not appeal the conditional approval.
Two (2) months after obtaining the county planning commission's
approval of the subdivision plan, the developer submitted a "private
request" to DEP to adopt the planning module as a revision
to the existing community sewage facilities plan. The Department
found that since the new sewage facilities plan submitted by the
township had not yet been approved, the developer was entitled
to approval of his sewage facilities planning module. DEP ordered
the township to adopt the module. The township then appealed to
the Environmental Hearing Board (EHB). The EHB reversed DEP, concluding
the the new sewage facilities plan had been "deemed approved"
when DEP failed to act on the submission within 120 days of the
submittal as required under Pa.Code Section 71.32.
The court upheld the decision of the Environmental Hearing Board.
The final decision included a number of complex procedural issues.
Most important to this summary the findings include a determination
that, as a matter of law, MPC 508(4)(i) does not afford a developer
protection against sewage facilities plan amendments. However,
the court also found that the 1992 sewage facilities plan adopted
by the township was " inadequate to meet the applicants sewage
disposal needs" and upheld the EHB's order that DEP grant
the developers private request.
The court discussed in detail the provisions of Act 537, Section
5(b) which permit a "private request" when a property
owner believes that a municipality's sewage facilities plan is
either not being implemented or is inadequate to serve the landowner's
sewage needs. (It is interesting to note that the final decision
came five (5) years after the final approval of the developer's
subdivision plan.
DISCLAIMER:
This site is designed to provide summary review of selected Pennsylvania
and Federal Court decisions related to land use and land use controls.
The information contained herein, although produced by professionals,
is not intended to render any legal service. Nor should the materials
herein be utilized as a substitute for professional services.
If legal advice or other expert assistance is required, the service
of an attorney or other professional should be sought. DCED makes
no representations, warranties or guarantees as to the accuracy,
completeness or suitability of the information provided herein.
Back to Top
|